How to Calculate Concrete for a Slab

Ordering concrete is one of those jobs where a small mistake gets expensive fast. Order too little and you’re stuck with a half-finished slab while the first section starts to set. Order too much and you’re paying for a pile of wet leftovers. The good news is that the math is simple. You need a tape measure and a phone calculator, nothing more.

This guide shows how to calculate concrete for a slab, step by step, with a real example. If you’d rather skip the arithmetic, the concrete calculator does the same steps for you and also gives you bag counts.

12 ft10 ft12 × 10 × 0.333= 40 cu ft ≈ 1.48 cu ydSide view4 in slabgravel base4 in = 0.333 ft
A 12 ft by 10 ft patio slab at 4 in thick needs about 40 cubic feet of concrete.

The formula in one line

Concrete is sold by volume, so you’re really just working out how much space the slab fills:

Volume = length × width × thickness

The catch is units. Length and width are usually in feet, but thickness is in inches. Divide the thickness by 12 to turn it into feet, then multiply. That gives cubic feet. Concrete suppliers sell by the cubic yard, and one cubic yard is 27 cubic feet, so divide by 27 at the end.

A worked example: a 12 ft × 10 ft patio, 4 inches thick

StepWorkingResult
1. Thickness in feet4 ÷ 120.333 ft
2. Volume in cubic feet12 × 10 × 0.33340 cu ft
3. Volume in cubic yards40 ÷ 271.48 cu yd
4. Add 10% extra1.48 × 1.101.63 cu yd

So you’d round up and ask for about 1¾ cubic yards. Most ready-mix suppliers think in quarter-yards, which is why rounding up like this is normal.

Why you should always add extra

Nobody pours onto a perfectly flat, perfectly level surface. The ground dips in places, the forms bow a little, and some concrete gets spilled or stuck in the wheelbarrow. A slab that’s a quarter-inch thicker than planned across 120 square feet adds up quicker than you’d think.

A 5% to 10% buffer is the usual range. Go closer to 10% if the subgrade is uneven or the job is awkward to reach. Go closer to 5% if you’ve graded carefully and the forms are tight.

How many bags do you need?

For small jobs you might mix bagged concrete yourself. Bags are labeled by weight, and each size fills a different amount of space. The yields below are typical, but check the bag, because brands vary a little.

Bag sizeYield (approx.)Bags for 40 cu ftBags for 44 cu ft (with 10% extra)
40 lb0.30 cu ft134147
60 lb0.45 cu ft8998
80 lb0.60 cu ft6774

Seventy-four 80 lb bags is a lot of lifting. Each bag weighs 80 pounds, so you’d be moving almost three tons of dry mix, and you’d need to mix and place it before it sets. That’s the point where most people stop and look at delivery.

Bags or ready-mix delivery?

As a rough guide, bags make sense for jobs under about one cubic yard, like a small pad, a few post footings, or a repair. Above one to two cubic yards, a delivered load is usually cheaper per yard and much easier on your back. It also gives you more consistent concrete, since one batch is mixed the same way from start to finish.

Ready-mix suppliers often charge a short-load fee when your order is below their minimum. Ask about it before you decide, because it can change which option is cheaper.

Working out the cost

Cost is just volume times price. If a local supplier quotes $160 per cubic yard (a made-up number, so use your own quote), 1.75 cubic yards comes to about $280 before delivery and any fees. Compare that with your bag price multiplied by the bag count and you’ll see which way the numbers lean. Prices change by region and season, so get a current quote.

Other shapes: footings and columns

The same idea works for other pours. A strip footing is still length × width × depth. For a footing 16 inches wide, 8 inches deep and 30 feet long:

  • 16 inches = 1.333 ft and 8 inches = 0.667 ft
  • 30 × 1.333 × 0.667 = 26.7 cubic feet
  • 26.7 ÷ 27 = 0.99 cubic yards

Round columns use the area of a circle (π × radius² × height). For stairs it’s easier to treat each step as a block and add them up, which is what the calculator does.

Mistakes that cost people money

  • Mixing units. Putting thickness in inches into a formula that expects feet is the classic one. A 4-inch slab is 0.333 ft, not 4.
  • Measuring the surface instead of the forms. Measure the finished size of the pour, including any thicker edges or footings that are poured with the slab.
  • Ordering the exact amount. There’s no such thing as an exact amount on a real job site.
  • Forgetting the base. Gravel under the slab isn’t concrete. Work out the gravel separately.
  • Skipping local requirements. Thickness for driveways, garage floors and anything carrying heavy loads depends on your soil, your climate and local code. A typical patio is 4 inches, but heavier use often calls for more, so check with your local building office or an engineer.

Quick checklist before you order

  1. Measure length, width and finished thickness.
  2. Convert thickness to feet and multiply to get cubic feet.
  3. Divide by 27 to get cubic yards.
  4. Add 5% to 10%.
  5. Round up to the nearest quarter-yard.
  6. Ask your supplier about delivery minimums and short-load fees.

If you want to check your numbers, run them through the concrete calculator. For the reinforcement that goes inside the slab, see our rebar calculator.

Related guides

See all construction and home project guides

This guide gives general estimates for planning. Materials, local codes and site conditions vary, so confirm the details for your project with a local supplier or professional.

Leave a Comment